Cerulean Winds - Aspen wind farm project
The Community Council wishes to thank all residents who responded to our call for help and advice regarding the Aspen Onshore Transmission Infrastructure Project. We have now submitted our response to Cerulean Winds‘ Environmental Impact Assessment Scoping Report. The Scoping Report is available from onshore consultation
You may email us at planning@nmccc.org.uk if you wish to make a comment.
The area outlined in red on the map shows the projected corridor of the route for cables passing Newtonhill.

There are three main aspects to this project that we would like you to consider: construction phase, built infrastructure, and community benefits provided by the developer.
Construction Phase
Cables will be run underground from landfall north of Newtonhill through to the Hurlie substation near Stonehaven. These cables will require a trench to be dug or conduits to be drilled. Work at Chapelton and the houses on the moor has shown that months of rock breaking may be required. New temporary and permanent roads may also be required.
Built infrastructure
The cables will need to be joined every 500 to 1000 metres. This will require an accessible structure of some sort. A second substation will be built that will require a footprint of 300 by 350 metres (about the size of 16 championship football pitches), along with the necessary access roads.
Community benefits provided by the developer
With this much disruption within our Community Council area, what do you think that the developers must do to compensate the community?
Available downloads from the developer:
Pre Application Consultation ProposalsOverview Map
Application Notice
Application Notice Boundary Plan
Aspen floating offshore windfarm
Developer consultation events in Newtonhill
Thursday 20 August, 1200-1900 at The Bettridge Centre
