Community Council Logo

Next Meeting

Wednesday 19th August
NEW start time: 7.00pm
Skateraw Hall, Newtonhill


Cerulean Winds - Aspen wind farm project

The Community Council wishes to thank all residents who responded to our call for help and advice regarding the Aspen Onshore Transmission Infrastructure Project. We have now submitted our response to Cerulean Winds‘ Environmental Impact Assessment Scoping Report. The Scoping Report is available from onshore consultation

You may email us at planning@nmccc.org.uk if you wish to make a comment.

The area outlined in red on the map shows the projected corridor of the route for cables passing Newtonhill.


There are three main aspects to this project that we would like you to consider: construction phase, built infrastructure, and community benefits provided by the developer.

Construction Phase

Cables will be run underground from landfall north of Newtonhill through to the Hurlie substation near Stonehaven. These cables will require a trench to be dug or conduits to be drilled. Work at Chapelton and the houses on the moor has shown that months of rock breaking may be required. New temporary and permanent roads may also be required.

Built infrastructure

The cables will need to be joined every 500 to 1000 metres. This will require an accessible structure of some sort. A second substation will be built that will require a footprint of 300 by 350 metres (about the size of 16 championship football pitches), along with the necessary access roads.

Community benefits provided by the developer

With this much disruption within our Community Council area, what do you think that the developers must do to compensate the community?

Available downloads from the developer:

Pre Application Consultation Proposals
Overview Map
Application Notice
Application Notice Boundary Plan
Aspen floating offshore windfarm

Visit Aspen onshore consultation for more information.

Developer consultation events in Newtonhill

Thursday 20 August, 1200-1900 at The Bettridge Centre